THESSALONIKI WILL BE ONE OF THE 141 CITIES IN THE WORLD THAT WILL HAVE A MODERN SUBWAY (METRO )









After the unsuccessful attempt to have the Thessaloniki Metro constructed by the Concession Contract method (1998-2003), in September 2003 the decision was made for this specific Project to be constructed by means of National and European Union funds.

On the basis of the new Invitation to Tender, in June 2004 five Joint Ventures consisting of major Greek and Foreign companies of the construction field expressed their interest in participating in this Tender. Its first phase was completed in November 2004.

Four of the five Joint Ventures were qualified to proceed to the second stage of the tender and in January 2005 they took delivery of the tender documents, as well the new advanced concept design of the Project. In May 12th 2005, the pre-selected Joint Ventures submitted their Technical and Financial Offers and in August 19th the Tender Committee completed the evaluation process of the Technical and Financial Offers submitted by the three Joint Ventures, which were accepted to participate in the final phase of the Tender.

The Contract with the Contracting Joint Venture AEGEK – IMPREGILO – ANSALDO T.S.F – SELI – ANSALDOBREDA was signed on April 7th 2006 and the construction of the Project commenced at the end of June 2006.

Decision for this Project to be tendered as Public Work 9/2003
Legislative regulation awarding the implementation of the Project to ATTIKO METRO 12/2003
Commencement of the procedure related to the pre-qualification of Contractors 12/2003
Submission of applications by candidates expressing their interest 6/2004

Completion of pre-qualification procedure
11/2004

Completion of the preparation of the design and tender documents by ATTIKO METRO
1/2005

2nd phase of the Project Tendering process
1/2005

Submission of Technical and Financial Offers
5/2005

Technical Evaluation of the bidding Joint Ventures
7/2005
Appointment of a provisional Contractor 8/2005
Conclusion of the Contract and initiation of the Project construction activities 4/2006


The construction of Thessaloniki Metro shall integrate state-of-the-art technology and the most demanding standards concerning both quality and operation, rendering it, thus, the most modern Metro System in the whole Europe.

The basic characteristics of the THESSALONIKI METRO network are the following:

A Depot in the Pylea Region (Votsi) covering a surface of 50,000 square meters.

13 modern center platform stations


9.5 km of Line (with two independent single track tunnels) constructed mostly (7.7 km) by means of two Tunnel Boring Machines. The remaining section of the Line will be constructed by the Cut and Cover method

18 ultra-automatic and state-of-the-art trains, fully air-conditioned, which will be run without a train driver, with an attendant aboard the train.


platform screen doors, which guarantee greater safety level


A Depot in the Pylea Region (Votsi) covering a surface of 50,000 square meters.

Within the framework of the same development plan, provision has been made for the development of underground parking facilities in Thessaloniki Metro network, their capacity being 3,700 places in total.

PARKING AREA

Neos Sidirodromikos Stathmos 1 450 -4 underground


Neos Sidirodromikos Stathmos 2 600 -4 underground


Nea Elvetia 650 -1, ground level, +2

Panepistimio 1 1000 -4 underground
Panepistimio 2 1000 -4 underground

TOTAL PLACES OF PARKING 3700


METRO MAPS ALL OVER THE WORLD :http://www.amadeus.net/home/new/subwaymaps/en/
INFORMATIONS ABOUT THESSALONIKI METRO : http://www.ametro.gr/page/